Jump to a key chapter
What is Earned Value Analysis?
Earned Value Analysis (EVA) is a critical project management methodology used to measure project performance and progress in an objective manner. By integrating the project scope, schedule, and cost, it allows you to evaluate if the project is on track to be completed on time and within budget.
Understanding the Components of EVA
There are three primary components you need to understand in earned value analysis:
- Planned Value (PV): This is the budgeted amount for the work scheduled to be completed by a specified date. It helps in evaluating whether the project is progressing as per the initial plan.
- Earned Value (EV): This represents the value of the actual work completed by a specified date. It allows you to measure the work performed against the original schedule.
- Actual Cost (AC): This is the actual expense incurred for the work completed by a specified date. It gives insight into the portion of the budget that has already been utilized.
Earned value calculation involves combining these components: - EV is calculated using the formula: \[ EV = \text{Percentage of Complete Work} \times \text{Total Project Budget} \] This helps to contextualize the actual progress of the project against the planned progress.
Calculating Cost and Schedule Variances
Once you understand the components, it's crucial to determine the project’s performance using cost and schedule variances:
- Cost Variance (CV): This is determined using the formula: \[ CV = EV - AC \] This calculates how much under or over the budget the project is at a given point.
- Schedule Variance (SV): Use this formula to measure schedule efficiency:\[ SV = EV - PV \] It indicates whether the project is ahead of or behind schedule.
For example, if a project has an EV of $20,000, AC of $18,000, and a PV of $22,000, then:
- Cost Variance (CV) would be:\[ CV = 20,000 - 18,000 = 2,000 \]
- Schedule Variance (SV) would be:\[ SV = 20,000 - 22,000 = -2,000 \]
Predictive Indicators in EVABeyond simple variances, you can also use predictive measures in Earned Value Analysis:
- Cost Performance Index (CPI): The formula is: \[ CPI = \frac{EV}{AC} \]This index indicates the cost efficiency of the project.
- Schedule Performance Index (SPI): Calculated as: \[ SPI = \frac{EV}{PV} \]It shows schedule efficiency.
Define Earned Value Analysis
Earned Value Analysis (EVA) is a systematic project management process to assess project performance and progress. It combines scope, schedule, and cost data to provide a comprehensive understanding of the project's health.
Earned Value Analysis evaluates project performance using three primary metrics:
- Planned Value (PV): The budgeted cost of work scheduled to be completed by a specific point in time.
- Earned Value (EV): The actual work completed in terms of its budgeted cost by a specific date.
- Actual Cost (AC): The actual expenditure for work completed by a particular date.
Calculating earned value involves understanding these metrics:
- Earned Value (EV) is calculated as:\[ EV = \text{Percentage of Work Completed} \times \text{Total Budget} \]
- Use PV and AC for more insights to determine the cost and schedule variances.
Analyzing Variances in Earned Value
Earned Value Analysis uses variances to assess project performance efficiency:
- Cost Variance (CV): Measures financial performance:\[ CV = EV - AC \]
- Schedule Variance (SV): Assesses if the project is on schedule:\[ SV = EV - PV \]
Assume a project with EV of $25,000, AC of $22,000, and PV of $28,000:
- Cost Variance (CV) is:\[ CV = 25,000 - 22,000 = 3,000 \]
- Schedule Variance (SV) is:\[ SV = 25,000 - 28,000 = -3,000 \]
Advanced Metrics in Earned Value AnalysisBeyond basic variances, you can delve deeper with indices:
- Cost Performance Index (CPI): Measures cost efficiency: \[ CPI = \frac{EV}{AC} \] A CPI greater than 1 indicates cost efficiency.
- Schedule Performance Index (SPI): Evaluates time efficiency: \[ SPI = \frac{EV}{PV} \] An SPI greater than 1 signifies being ahead of schedule.
A project is considered healthy if both the CPI and SPI are equal to or greater than 1. This reflects both cost and schedule efficiency.
Earned Value Analysis in Project Management
Earned Value Analysis (EVA) is a powerful tool used in project management to assess a project's performance. By integrating cost, schedule, and scope, EVA provides a comprehensive view of how well a project is progressing relative to its plan.
Key Components of Earned Value Analysis
To effectively apply earned value analysis, you should understand its key components:
- Planned Value (PV): Also known as Budgeted Cost of Work Scheduled (BCWS), PV is the estimated cost of the planned project activities up to a particular time.
- Earned Value (EV): Known as Budgeted Cost of Work Performed (BCWP), EV is the value of actual work completed in terms of the approved budget.
- Actual Cost (AC): Also called Actual Cost of Work Performed (ACWP), AC is the total cost incurred for the work performed.
The formula for Earned Value (EV) is: \[ EV = \text{Percentage of Work Completed} \times \text{Total Project Budget} \]
Evaluating Project Performance with Variances
Cost and schedule variances are vital for measuring project health:
- Cost Variance (CV): This indicates the financial performance compared to the planned budget. It is calculated as:\[ CV = EV - AC \]
- Schedule Variance (SV): This metric evaluates schedule performance. It is calculated as:\[ SV = EV - PV \]
Consider a project where the EV is $30,000, the AC is $28,000, and the PV is $32,000:
- Cost Variance (CV) is:\[ CV = 30,000 - 28,000 = 2,000 \]
- Schedule Variance (SV) is:\[ SV = 30,000 - 32,000 = -2,000 \]
Advanced Metrics for In-depth AnalysisBeyond simple variance calculations, you can use indices to further analyze project performance over time:
- Cost Performance Index (CPI): It measures cost efficiency and is calculated as: \[ CPI = \frac{EV}{AC} \] A CPI greater than 1 indicates the project is performing better than expected.
- Schedule Performance Index (SPI): This index measures time efficiency, calculated as: \[ SPI = \frac{EV}{PV} \] An SPI greater than 1 signifies the project is ahead of schedule.
A balanced approach using both CPI and SPI helps in maintaining project cost and time efficiency. Keeping both indices equal to or greater than 1 indicates favorable project performance.
How to Calculate Earned Value Analysis
Understanding Earned Value Analysis (EVA) is essential for managing the progress and performance of a project effectively. This methodology integrates scope, time, and cost, allowing you to determine if a project is on track.
Earned Value Analysis Formula Breakdown
To accurately assess project performance, you should focus on three main components in earned value analysis:
- Planned Value (PV): This represents the estimated amount allocated for the work planned by a particular date.
- Earned Value (EV): This metric reflects the value of the work actually completed, measured against the budgeted cost.
- Actual Cost (AC): It is the real cost incurred for the work done by that same date.
Component | Description |
Planned Value (PV) | Estimated cost of scheduled work |
Earned Value (EV) | Budgeted value of completed work |
Actual Cost (AC) | Actual expenditure for completed work |
Earned Value (EV) can be calculated using:\[ EV = \frac{\text{Work Completed (\text{%})}}{100} \times \text{Total Budget} \]This formula is crucial to contextually understanding the project's development.
Let's say you have a project with 60% completion, and a total budget of $50,000. The Earned Value (EV) would be:\[ EV = \frac{60}{100} \times 50,000 = 30,000 \]This indicates $30,000 worth of work budgeted is achieved.
In addition to understanding basic components, utilizing advanced performance measurements can provide deeper insights:
- Cost Performance Index (CPI): This index indicates the cost efficiency and is formulated as:\[ CPI = \frac{EV}{AC} \]A value greater than 1 implies cost effectiveness.
- Schedule Performance Index (SPI): Represents schedule efficiency with the formula:\[ SPI = \frac{EV}{PV} \]A value greater than 1 signifies the project is running ahead of schedule.
Understanding Earned Value Analysis
In project management, Earned Value Analysis offers a quantitative approach to track the progress and efficiency of a project. It's a comprehensive analysis technique that combines planned value, earned value, and actual cost to gauge current project performance and forecast future project potential.
Consider a scenario where a project's EV is $40,000, the AC is $35,000, and the PV is $45,000:
- The Cost Variance (CV) calculation:\[ CV = EV - AC = 40,000 - 35,000 = 5,000 \]This variance indicates that the project is $5,000 under budget.
- The Schedule Variance (SV) calculation:\[ SV = EV - PV = 40,000 - 45,000 = -5,000 \]This result suggests that the project is $5,000 behind schedule.
A project is deemed efficient if both its CPI and SPI are greater than or equal to 1, indicating effective management of both cost and schedule.
earned value analysis - Key takeaways
- Earned Value Analysis (EVA): A project management methodology to measure project performance objectively by integrating scope, schedule, and cost.
- Components of EVA: Includes Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to evaluate project progress against the plan.
- Earned Value (EV) Calculation: Formula: EV = Percentage of Complete Work x Total Project Budget, for contextualizing project progress.
- Variance Analysis in EVA: Cost Variance (CV) = EV - AC, and Schedule Variance (SV) = EV - PV indicate budget and schedule performance.
- Performance Indices: Cost Performance Index (CPI = EV/AC) and Schedule Performance Index (SPI = EV/PV) gauge efficiency; values >1 indicate success.
- EVA in Project Management: A comprehensive tool integrating cost, schedule, and scope to monitor project progress relative to the plan.
Learn with 12 earned value analysis flashcards in the free StudySmarter app
We have 14,000 flashcards about Dynamic Landscapes.
Already have an account? Log in
Frequently Asked Questions about earned value analysis
About StudySmarter
StudySmarter is a globally recognized educational technology company, offering a holistic learning platform designed for students of all ages and educational levels. Our platform provides learning support for a wide range of subjects, including STEM, Social Sciences, and Languages and also helps students to successfully master various tests and exams worldwide, such as GCSE, A Level, SAT, ACT, Abitur, and more. We offer an extensive library of learning materials, including interactive flashcards, comprehensive textbook solutions, and detailed explanations. The cutting-edge technology and tools we provide help students create their own learning materials. StudySmarter’s content is not only expert-verified but also regularly updated to ensure accuracy and relevance.
Learn more